Step 1 Offload Materials
Step 2 Prepare Slab
Step 3 Mark and Drill Slab
Step 4 Lay Out First Portal
Step 5 Cut Knee Braces
Step 6 Cut and Install Apex Braces
Step 7 Install Eave Purlin Brackets and other column components
Step 8 Mark Girt and Purlin Locations on Columns & Rafters
Step 9 Complete Assembly of Portals
Step 10 Install First Columns
Step 11 Install Eave Purlins and Sidewall Girts
Step 12 Install X-Bracing in First Sidewall Bay
Step 13 Install Rafters & Knee Braces in First Bay
Step 14 Install Purlins and Roof X-Bracing
Step 15 Construct Adjacent Bays
Step 16 Install Leanto Bays
Step 17 Install Door Framing
Step 18 Install Base, Rake Angle and FlyBracing
Step 19 Install Wall Sheeting and Insulation
Step 20 Install Corner Trim
Step 21 Install Leanto Roof Sheeting
Step 22 Install Pelmet (if applicable) and Eave Trim
Step 23 Install Insulation and Sheeting on Main Roof
Step 25 Install Rake Trim
Step 26 Install Ridge Cap
Step 27 Install Gutters
Step 28 Install Gutter Downspouts
Step 29 Install All Doors
Step 1 Install Mezzanine floor Brackets
Step 2 Install Mezzanine Girders
Step 3 Install Mezzanine Posts
Step 4 Install Mezzanine Joists
Step 5 Install Mezzanine Flooring
Roofing & steel building industry information, product updates, new releases, special offers, news and more direct from our corporate office.
Thank you for subscribing.
We will be in your inbox soon.
Copyright 2024 Mid Florida Metal Roofing Supply, Inc. | All Rights Reserved | Designed by Yeppy Marketing Agency | Privacy Policy